under The Inter State Migrant Workmen (Regulation of Employment and Conditions of Service) Act, 1979
under Motor Transport Workers Act, 1961
Conducted by Regional Labour Offices under jurisdiction of Joint Labour Commissioner, North Bengal Zone
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Principal Employer.
If Offine/Manual certificate available
select ALREADY REGISTERED option from menu and apply for online application of Principal Employer under the Contract Labour (Regulation and Abolition) Act , 1970 by filling up necessary information in the Form and uploads self-certified copies of required documents.NEW REGISTRATION: Select NEW REGISTRATION from menu and applies for online Registration of Principal Employer under the Contract Labour (Regulation and Abolition) Act , 1970 by filling up necessary information in the Form and uploads self-certified copies of required documents.
Documents Involved: I.Valid Trade License, II.Articles of Association and Memorandum of Association/Partnership Deed, III.Factory License if any, IV.Other certificates of registration in case of other than company, proprietorship or partnership firm like cooperative, Trustees etc., V.Any other document in support of correctness of the particulars mentioned in the application if required
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
1 | Assistant Labour Commissioner | 30 days |
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 2 | Verifies the application and allows for payment | ALC | Preferably 15 days |
STEP 3 | Submits fee and uploads FORM-I | Application | 0 (zero) days |
STEP 4 | Verifies and issue certificate/ Back for correction | ALC | Preferably 15 days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Number of Workmen | Fees |
---|---|---|
1 | Is 10 but does not exceed 20 | ₹200 |
2 | Exceeds 20 but does not exceed 50 | ₹500 |
3 | Exceeds 50 but does not exceed 100 | ₹1000 |
4 | Exceeds 100 but does not exceed 200 | ₹2000 |
5 | Exceeds 200 but does not exceed 400 | ₹4000 |
6 | Exceeds 400 | ₹5000 |
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Principal Employer.
AMENDMENT: Select AMENDMENT from menu and applies for Amendment of Registration Certificate of Principal Employers under the Contract Labour (Regulation and Abolition) Act , 1970 by filling up necessary information in the Form and uploads self-certified copies of required documents.
Documents Involved: I.Valid Trade License, II.Articles of Association and Memorandum of Association/Partnership Deed, III.Factory License if any, IV.Other certificates of registration in case of other than company, proprietorship or partnership firm like cooperative, Trustees etc., V.Any other document in support of correctness of the particulars mentioned in the application if required
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
1 | Assistant Labour Commissioner | 30 days |
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 2 | Verifies the application and allows for payment | ALC | Preferably 15 days |
STEP 3 | Submits fee and uploads FORM-I | Application | 0 (zero) days |
STEP 4 | Verifies and issue certificate/ Back for correction | ALC | Preferably 15 days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Number of Workmen | Fees |
---|---|---|
1 | Does not exceed less or equal to 20 | ₹200 |
2 | Exceeds 20 but does not exceed 50 | ₹500 |
3 | Exceeds 50 but does not exceed 100 | ₹1000 |
4 | Exceeds 100 but does not exceed 200 | ₹2000 |
5 | Exceeds 200 but does not exceed 400 | ₹4000 |
6 | Exceeds 400 | ₹5000 |
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Contractor
Responsibility: Contractor
Responsibility: Contractor.
Responsibility: Principal Employer
Responsibility: Principal Employer.
Responsibility: Contractor
Documents Involved: I.Valid Form V, II.Valid Work Order, III.Any other documents in support of correctness of particulars furnished in application form, IV.Trade license
Responsibility: Contractor
Responsibility: Contractor
Responsibility: Contractor
Responsibility: Inspector concerned
Responsibility: Inspector concerned
Responsibility: Inspector concerned
Responsibility: Inspector concerned
Responsibility: Inspector concerned
Responsibility: Contractor
Responsibility: Contractor
Documents Involved: I.Valid Work Order, II.Any other documents in support of correctness of particulars furnished in application form,III.Valid Form V, IV.Trade license
Responsibility: Inspector concerned
Responsibility: Inspector concerned
Responsibility: ALC of the Subdivision
Responsibility: ALC of the Subdivision
Responsibility: Contractor
Responsibility: Contractor
Responsibility: Contractor
Document Involved: I. Original signed application, II.Proof of submission of fees and security deposit
Responsibility: ALC of the Subdivision
Responsibility: ALC of the Subdivision
Responsibility: Contractor
Responsibility: Contractor
Responsibility: Inspector Concerned
Responsibility: Contractor
Documents Involved: I.Valid Work Order, II.Any other documents in support of correctness of particulars furnished in application form,III.Valid Form V, IV.Trade license
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
1 | Assistant Labour Commissioner | 30 days |
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 2 | Verifies the application and allows for payment | ALC | Preferably 15 days |
STEP 3 | Submits fee and uploads FORM-IV | Application | 0 (zero) days |
STEP 4 | Verifies and issue certificate/ Back for correction | ALC | Preferably 15 days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Number of Workmen | Fees |
---|---|---|
1 | Is 10 but does not exceed 20 | ₹50 |
2 | Exceeds 20 but does not exceed 50 | ₹125 |
3 | Exceeds 50 but does not exceed 100 | ₹250 |
4 | Exceeds 100 but does not exceed 200 | ₹500 |
5 | Exceeds 200 but does not exceed 400 | ₹1000 |
6 | Exceeds 400 | ₹1250 |
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Contractor
Responsibility: Contractor
Responsibility: Contractor.
Responsibility: Contractor
Documents Involved: I.Extended Work Order
Responsibility: Contractor
Responsibility: Contractor
Responsibility: Contractor
Document Involved: I. Signed FORM VII
Responsibility: Contractor
Responsibility: Contractor
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 3 | Submits fee and uploads FORM-VII | Application | 0 (zero) days |
STEP 4 | Auto-generated Renewal certificate | Auto-Renewal | 0 (zero) days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Number of Workmen | Fees |
---|---|---|
1 | Is 10 but does not exceed 20 | ₹50 |
2 | Exceeds 20 but does not exceed 50 | ₹125 |
3 | Exceeds 50 but does not exceed 100 | ₹250 |
4 | Exceeds 100 but does not exceed 200 | ₹500 |
5 | Exceeds 200 but does not exceed 400 | ₹1000 |
6 | Exceeds 400 | ₹1250 |
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Contractor.
AMENDMENT: Select AMENDMENT of License from menu and applies for Amendment of License under the Contract Labour (Regulation and Abolition) Act , 1970 by filling up necessary information which needs to be amended in the Form and uploads self-certified copies of required documents.
Documents Involved: I.Work Order, II.Residential Certificate/Trade License, III.Other Document
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
1 | Assistant Labour Commissioner | 30 days |
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 2 | Verifies the application and allows for payment | ALC | Preferably 15 days |
STEP 3 | Submits fee and uploads FORM-VII | Application | 0 (zero) days |
STEP 4 | Verifies and issue certificate/ Back for correction | ALC | Preferably 15 days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Number of Workmen | Fees |
---|---|---|
1 | Is 10 but does not exceed 20 | ₹50 |
2 | Exceeds 20 but does not exceed 50 | ₹125 |
3 | Exceeds 50 but does not exceed 100 | ₹250 |
4 | Exceeds 100 but does not exceed 200 | ₹500 |
5 | Exceeds 200 but does not exceed 400 | ₹1000 |
6 | Exceeds 400 | ₹1250 |
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Principal Employer.
NEW REGISTRATION: Select NEW REGISTRATION from menu and applies for online Registration of Principal Employer under The Inter State Migrant Workmen (Regulation of Employment and Conditions of Service) Act, 1979 by filling up necessary information in the Form and uploads self-certified copies of required documents.
Documents Involved: I.Valid Trade License, II.Articles of Association and Memorandum of Association/Partnership Deed, III.Factory License if any, IV.Certificate issued by Authorities from other state., V.Documents substantiating correctness of particulars mentioned in the application
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
1 | Assistant Labour Commissioner | 30 days |
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 2 | Verifies the application and allows for payment | ALC | Preferably 15 days |
STEP 3 | Submits fee and uploads FORM-I | Application | 0 (zero) days |
STEP 4 | Verifies and issue certificate/ Back for correction | ALC | Preferably 15 days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Number of Workmen | Fees |
---|---|---|
1 | Is 5 or more but does not exceed 20 | ₹30 |
2 | Exceeds 20 but does not exceed 50 | ₹75 |
3 | Exceeds 50 but does not exceed 100 | ₹150 |
4 | Exceeds 100 but does not exceed 200 | ₹300 |
5 | Exceeds 200 but does not exceed 400 | ₹600 |
6 | Exceeds 400 but does not exceed 800 | ₹900 |
7 | Exceeds 800 but does not exceed 1000 | ₹1000 |
8 | Exceeds 1000 | ₹1500 |
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Employer.
NEW REGISTRATION: Select NEW REGISTRATION from menu and applies for online Registration of Establishments under the Building and Other Construction Workers (RE&CS) Act , 1996 by filling up necessary information in the Form and uploads self-certified copies of required documents.
Documents Involved: I.Valid Trade License, II.Articles of Association and Memorandum of Association/Partnership Deed, III.Any other document in support of correctness of the particulars mentioned in the application if required, IV.Other certificates of registration in case of other than company, proprietorship or partnership firm like cooperative, Trustees etc., V.Challan, VI.Work Order, VII.FORM-I for assesment of CESS, VIII. Documents in Support of Payment of CESS, IX. Documents in Support of Correctness of Application, X. Address Proof
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
1 | Assistant Labour Commissioner | 30 days |
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 2 | Verifies the application and allows for payment | ALC | Preferably 15 days |
STEP 3 | Submits fee and uploads FORM-I | Application | 0 (zero) days |
STEP 4 | Verifies and issue certificate/ Back for correction | ALC | Preferably 15 days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Number of Workmen | Fees |
---|---|---|
1 | Is upto 100 | ₹500 |
2 | Exceeds 100 but does not exceed 500 | ₹2000 |
3 | Exceeds 500 | ₹10000 |
Responsibility: Trade Union Applicant
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
Not Available |
Responsibility: FAWLOI Declaration Submit
Documents Involved: All file should be PDF/JPG/JPEG/PNG(150 KB) except Photograph. Photograph should be JPG/JPEG/PNG(50 KB)
Documents Involved: The Declaration form with Signature of the Beneficiary and Signature of the Secretary of Registered Trade Union of the concerned unit along with Registration no. / Local MLA / Local MP with official Seal.
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
Not Available |
Responsibility: Motor Transport Undertaking
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Documents Involved: I.Trade License, II. Article of Association / Partnership Deed, III. Blue Book/ Smart Card Issued by Motor Vehicles, IV. Insurance Certificate of Motor Vehicles, V. Address Proof, VI. Documents substantiating correctness of particulars mentioned in the application.
Comprehensive list of documents required for application are same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location (Rural, Urban).
Sl.No. | Designated officer | Stipulated time limit |
---|---|---|
1 | Assistant Labour Commissioner | 30 days |
Step No. | Procedure | Official Involved | Timeline |
---|---|---|---|
STEP 1 | Applicant submits the application along with documents | Applicant | 0 (zero) days |
STEP 2 | Verifies the application and allows for payment | ALC | Preferably 15 days |
STEP 3 | Submits fee and uploads FORM-I | Application | 0 (zero) days |
STEP 4 | Verifies and issue certificate/ Back for correction | ALC | Preferably 15 days |
Fees required is same irrespective of risk category (Low, Medium, High), size of firm (Micro, Small, Medium & Large), Investor type (Foreign, Domestic), Business location ( Rural, Urban).
Sl.No. | Maximum number of workers employed to be employed during the year |
Fees |
---|---|---|
1 | 5 | ₹10 |
2 | 25 | ₹25 |
3 | 50 | ₹50 |
4 | 100 | ₹100 |
5 | 250 | ₹250 |
6 | 500 | ₹500 |
6 | 750 | ₹750 |
7 | 1000 and above | ₹1000 |
Procedure to be followed by the applicant and step by step movement of the application within the Department along with timelines for completion of each step is same irrespective of risk category (Low, Medium, High) size of firm (Micro, Medium & Large), Investor type (Foreign Domestic), Business location (Rural, Urban).
Procedure to be followed by applicant:
Responsibility: Motor Transport Undertaking.
Responsibility: